Completed works:

  • Completed brickwork to stairs
  • Demolished structural beams in O’Neil Building adjoining the new Wingaru Building.
  • Installed electrical submains from substation to main switchboard
  • Installed electrical submains from main switchboard to Wallace switchboard
  • Installed electrical submains from main switchboard to distribution boards on all levels
  • Installed mechanical chiller equipment and cooling towers

Upcoming Works:

  • Continue sheeting of walls and ceilings
  • Continue installation of windows
  • Complete stair 3 structural walls and stairs
  • Continue facade installation
  • Continue lift installation
  • Continue external wall framing to plant rooms