Completed Works
- Completed Level 3 formwork, and reinforcement
- Poured Level 3 concrete slab
- Poured walls and columns from Level 2 to Level 3
- Demolition works to O’Neil Building
- Completed batter works to Gartlan roundabout
- Continued with investigation works for substation cabling
- Prepared for basement slab construction and in-ground service
- Civil works around substation and gas bunker
Upcoming Works
- Pour walls and columns from Level 3 to Level 4
- Complete Level 4 formwork, and reinforcement
- Concrete pour for Level 4
- Continue works for substation cabling and prepare for substation installation
- Formwork reinforcement and concrete pour to basement slab
- Stripping of formwork to lower levels