Completed Works

  • Completed Level 3 formwork, and reinforcement
  • Poured Level 3 concrete slab
  • Poured walls and columns from Level 2 to Level 3
  • Demolition works to O’Neil Building
  • Completed batter works to Gartlan roundabout
  • Continued with investigation works for substation cabling
  • Prepared for basement slab construction and in-ground service
  • Civil works around substation and gas bunker

 

Upcoming Works

  • Pour walls and columns from Level 3 to Level 4
  • Complete Level 4 formwork, and reinforcement
  • Concrete pour for Level 4
  • Continue works for substation cabling and prepare for substation installation
  • Formwork reinforcement and concrete pour to basement slab
  • Stripping of formwork to lower levels