Completed Works

  • Formed and poured Ground Level walls, columns, and lift shaft.
  • Poured Ground Level suspended slab.
  • Erected scaffold to Ground Level.
  • Carried out investigation works for substation cabling.
  • Commenced internal strip out to Levels 2 & 3 of the O’Neil Building.

 

Upcoming Works

  • Continuation of formwork and reinforcement to Level 1.
  • Pouring of Level 1 slab.
  • Construction of concrete walls, columns, and lift shaft from Level 1 to Level 2.
  • Erect scaffold from Level 1 to Level 2.
  • Commencement of formwork to Level 2 suspended slab.
  • Continuation of investigation works for substation cabling.
  • Structural demolition to existing O’Neil Building.