Completed Works

  • Constructed lift and stair 2 shafts to roof level
  • Erected lower roof structural steel
  • Constructed basement masonry walls
  • Stripped and removed formwork to level 2 and Level 3
  • Constructed spandrel walls for Level 1
  • Installed wall and partition to Level 1
  • Installed high level services to Basement, Level 0 and Level 1
  • Installed mechanical units and ductwork to Level 0
  • Delivered and place substation
  • Extended electrical submains to Wallace Building
  • Gartlan roundabout widening (south side)

 

Upcoming works

  • Erect upper roof structural steel
  • Construct spandrel walls to Level 2 and Level 3
  • Install glazing frames to Level 1
  • Install walls and partitions for Basement, Level 0 and Level 1
  • Continue with high level rough-in to Level 2 and Level 3
  • Commence external civil works