Completed Works
- Constructed lift and stair 2 shafts to roof level
- Erected lower roof structural steel
- Constructed basement masonry walls
- Stripped and removed formwork to level 2 and Level 3
- Constructed spandrel walls for Level 1
- Installed wall and partition to Level 1
- Installed high level services to Basement, Level 0 and Level 1
- Installed mechanical units and ductwork to Level 0
- Delivered and place substation
- Extended electrical submains to Wallace Building
- Gartlan roundabout widening (south side)
Upcoming works
- Erect upper roof structural steel
- Construct spandrel walls to Level 2 and Level 3
- Install glazing frames to Level 1
- Install walls and partitions for Basement, Level 0 and Level 1
- Continue with high level rough-in to Level 2 and Level 3
- Commence external civil works