Completed Works:

  • Tiling to bathrooms in Wingaru Building
  • Commenced floor grinding to common areas
  • Installation of brackets to vertical sunshades
  • Window installation to Wingaru Building
  • Facade installation to Wingaru Building
  • Installed horizonal sunshades to northern facade
  • Commenced Chiller and cooling tower pipework
  • Installation of perforated plasterboard to common areas on Level 1,2 and 3 of Wingaru Building
  • Rendering works to Canteen and Basement
  • Commenced joinery installation
  • Retaining wall construction to northern landscaped area
  • Stair 3 Construction
  • High level rough in of services to O’Neil Building
  • Installed windows to canteen serving areas
  • Installation of metal track work to Cola ceiling

Upcoming Works:

  • Install vertical sunshades to eastern and northern facades
  • Continue scaffold removal to southern facade
  • Continue floor grinding to common areas
  • Commence floor preparation works to classrooms and house areas
  • Commence stud wall construction to O’Neil Building
  • Commence exit driveway retaining wall footings
  • Continue plant room fit out
  • Commence fit out works to Canteen, Print Room and Multi-purpose Room