Completed Works:
- Tiling to bathrooms in Wingaru Building
- Commenced floor grinding to common areas
- Installation of brackets to vertical sunshades
- Window installation to Wingaru Building
- Facade installation to Wingaru Building
- Installed horizonal sunshades to northern facade
- Commenced Chiller and cooling tower pipework
- Installation of perforated plasterboard to common areas on Level 1,2 and 3 of Wingaru Building
- Rendering works to Canteen and Basement
- Commenced joinery installation
- Retaining wall construction to northern landscaped area
- Stair 3 Construction
- High level rough in of services to O’Neil Building
- Installed windows to canteen serving areas
- Installation of metal track work to Cola ceiling
Upcoming Works:
- Install vertical sunshades to eastern and northern facades
- Continue scaffold removal to southern facade
- Continue floor grinding to common areas
- Commence floor preparation works to classrooms and house areas
- Commence stud wall construction to O’Neil Building
- Commence exit driveway retaining wall footings
- Continue plant room fit out
- Commence fit out works to Canteen, Print Room and Multi-purpose Room