Completed Works:
- Installed cladding to northern facades
- Commenced scaffold removal to southern facade
- Continued floor grinding to common areas
- Commenced floor preparation works to classrooms and house areas
- Commenced stud wall construction to O’Neil Building
- Commenced exit driveway retaining wall footings
- Continued plant room fit out
- Commenced fit out works to Canteen, Print Room and Multi-Purpose Room
Upcoming Works:
- Install vertical sunshades to facades
- Continue with scaffold removal
- Continue floor grinding and preparation to common areas
- Continue installation of vinyl & rubber to classrooms and house areas
- Continue stud wall & ceiling construction to O’Neil Building
- Complete services rough in for O’Neil Building
- Continue exit driveway retaining wall footings
- Complete plant room fit out
- Continue fit out works to Canteen, Print Room and Multi-Purpose Room
- Fit out of classrooms to Wingaru Building