Completed Works:

  • Installed cladding to northern facades
  • Commenced scaffold removal to southern facade
  • Continued floor grinding to common areas
  • Commenced floor preparation works to classrooms and house areas
  • Commenced stud wall construction to O’Neil Building
  • Commenced exit driveway retaining wall footings
  • Continued plant room fit out
  • Commenced fit out works to Canteen, Print Room and Multi-Purpose Room

Upcoming Works:

  • Install vertical sunshades to facades
  • Continue with scaffold removal
  • Continue floor grinding and preparation to common areas
  • Continue installation of vinyl & rubber to classrooms and house areas
  • Continue stud wall & ceiling construction to O’Neil Building
  • Complete services rough in for O’Neil Building
  • Continue exit driveway retaining wall footings
  • Complete plant room fit out
  • Continue fit out works to Canteen, Print Room and Multi-Purpose Room
  • Fit out of classrooms to Wingaru Building