Completed Works
- Completed installation of services to Basement level.
- Construction of curved wall to Basement level.
- Construction of formwork to Ground level suspended slab.
- Internal strip out to O’Neil Building.
- Continuation of works to widen eastern side of Loyola Drive.
- Carried out piling works to Podium level.
- Construction of concrete walls to Ground level.
- Commenced formwork to Level 1 (O’Neil Building).
Upcoming Works
- Installation of steel reinforcement and post tensioning to Ground level suspended slab.
- Installation of services to Ground level suspended slab.
- Pouring of Ground level suspended slab.
- Construction of concrete walls and upstands from Ground level to Level 1.
- Construction of concrete columns from Ground level to Level 1.
- Scaffold erected from Ground level to Level 1.