Completed Works

  • Continued setting of walls and sanding ceilings
  • Continued internal painting
  • Continued installation of windows
  • Completed facade installation
  • Completed lift installation
  • Continued Stair 3 construction
  • Completed cable installation for substation works
  • Commenced external retaining wall works
  • Commenced installation of joinery items

Upcoming Works

  • Continuing bathroom fit out
  • Continue internal painting
  • Install doors and hardware
  • Continue install joinery items
  • Commence floor preparation
  • Commence removal of external scaffold
  • Complete Stair 3 construction