Completed works
- Completed construction of lift walls to Basement level.
- Waterproofing and installation of drainage to lift pit.
- Construction of reinforced concrete columns to Basement and Ground Level.
- Construction of footings to Ground Level .
Upcoming works
- Continue construction of suspended slab.
- Continue construction of slab on Ground Level.
- Construction of Ground Level walls.
- Pouring of lift and stair walls.
- Installation of drainage across Loyola Drive.
- Installation of hoardings to O’Neil Building.
- Commencement of works to widen eastern side of Loyola Drive.