Completed Works
- Completed formwork reinforcement and concrete pour to Level 1
- Constructed concrete walls, columns and lift shaft from Level 1 to Level 2
- Commenced formwork to Level 2
- Erected scaffold from Level 1 to Level 2
- Prepared for structural demolition works to O’Neil Building
- Continued with investigation works for substation cabling
Upcoming Works
- Complete Level 2 formwork
- Install Level 2 reinforcement and services penetrations
- Erect scaffold from Level 2 to Level 3
- Pour walls and columns from Level 2 to Level 3
- Commence pouring Level 3 slab
- Demolition works to O’Neil Building
- Complete batter works to Gartlan roundabout
- Continue with investigation works for substation cabling
- Commence basement slab construction