Works in Progress

  • Continue services investigation works.
  • Demolition works, including removing Therry basketball courts.
  • Carry out services diversions within the main construction site.

 

Completed Works

  • Construction site access and exit.

 

Enabling, Excavation and ASP1 Electrical Works

  • Commence services investigations to the site area.
  • Complete trenching and cabling works required to divert the High Voltage Power Line from the site area.
  • Installed under road stormwater crossings, including associated pits outside of the site area.
  • Handover and commissioning of the new Father Mac Roundabout.
  • Opening of the College Staff carpark.
  • Amended existing line marking along Loyola Drive and the College Staff carpark.
  • Establishment of Belmadar loading zone.
  • Amended existing hoarding alongside O’Neil Building.
  • Installed a scaffold bridge to Belmadar’s site access, separating construction access from student access paths.
  • Installed additional site sheds and amenities to the project compound area in preparation for increased work activities.